Actual Achievement

LOGISTEED, Ltd. – Tsuchiura Logistics Center Phase 2 construction

Client
Hitachi Transport System, Ltd.
Planning site
2644-1 Shimoinayoshi Kasumigaura-shi, Ibaraki-ken 315-0052
Site area
25,439.86㎡ (7,695.56坪)
Construction area
6,073.36㎡( 1,837.19坪) Annex portion only
Total floor area
11,159.73㎡( 3,375.81坪) Annex portion only
Use
Warehouse
Structure and Scale
2 story steel structure
Construction period
3/1/2016 - 12/20/2016