Actual Achievement

Miyagi Co-op Joint Purchasing Sendai Central Center New construction

Client
Miyagi Consumers Cooperative Society
Planning site
3 Chome-1-1 Nigatake Miyagino-ku, Sendai-shi, Miyagi-ken 983-0036
Site area
9161.24㎡(2771.27坪)
Construction area
3107.79㎡(940.10坪)
Total floor area
3082.90㎡(932.57坪)
Use
Logistics Center
Structure and Scale
1 story steel structure
Construction period
11/28/2016 - 5/25/2017
F&P`s Role

This is the 3rd project from Miyagi COOP which covers design and supervision. Like the previous project F&P was involved from the development stage finding the location, basic designing, implementation design and construction supervision.
The facility was designed to taking into work efficiency and BCP for the employees. In considering an efficient work flow, arrival and departure exits were separated. Also for the employees, a break room was made as well as a roof top for staff to go outside to. For BCP benches on the roof top can be converted into kitchen ranges.